Rezoning a Kirksville property is not an over-the-counter permit.
It is a formal land-use process involving public notice, the Planning & Zoning Commission and a final City Council decision.
Before applying, first make sure rezoning is actually the correct tool.
Start by checking the existing zoning
A property owner should first confirm:
- current zoning district;
- proposed use;
- whether the use is already permitted;
- whether a Special Use Permit might be the appropriate path instead.
Do not request a zoning-map change simply because the current use is inconvenient.
The City treats rezoning and Special Use Permits as separate processes.
What does the City require for a rezoning application?
Current City zoning guidance lists materials including:
- Project Inquiry Form;
- Agent Authorization Form when applicable;
- Rezoning Application;
- application fee.
The City then works with the applicant through its planning and review process.
Check the current form for submission deadlines and fees before filing.
Why is an abstract company involved?
The City's current process requires the applicant to use an abstract company for the property information and nearby-owner notification step.
The abstract company obtains the detailed legal description and identifies adjacent owners within the required notice distance.
This is more precise than simply mailing letters to whoever appears nearby on a consumer map.
Nearby owners receive certified notice
Current City guidance requires certified notice to adjacent landowners within 185 feet.
The process also requires documentation showing that the notification requirement was completed.
That means neighbor notice is a formal part of the rezoning process, not an informal courtesy.
The City publishes public-hearing notice
The City Planner publishes notice of the intent to rezone at least 15 days before the public hearing in a newspaper of general circulation.
The notice identifies the property, hearing information and the current and proposed zoning.
Planning & Zoning hears the request
The request goes before the Planning & Zoning Commission.
The Commission holds the public hearing and makes a recommendation.
A favorable P&Z recommendation is not final approval.
City Council makes the final decision
The rezoning request then goes to City Council for the final decision at a later regular meeting.
Rezoning is discretionary.
Neither staff review nor a Commission recommendation guarantees that Council will approve the map change.
Give the process enough lead time
Rezoning requires:
- forms;
- legal-description work;
- neighbor notice;
- newspaper notice;
- meeting schedules;
- Commission review;
- Council action.
That means it should not be treated like a last-minute paperwork step after a lease is signed or construction is scheduled.
For a business, zoning should be checked before major financial commitments. See Starting a Business in Kirksville.
The important distinction is:
permit = permission under existing rules
rezoning = request to change the land-use rules applying to the property